A project manager is tasked with the planning of a new network installation for a client. The client wants to ensure that everything discussed in the meetings will be installed and configured when a network engineer arrives onsite. Which of the following should the project manager provide the client?

A. Acceptable Use Policy
B. Service Level agreement
C. Statement of work
D. Security Policy

Correct Answer: C
Section: Mix questions