Project+ PK0-004 Practice – Question263

During the planning phase of a construction project, the project team discovers the site is the nesting area birds, and construction could disrupt the birds patterns. Lobbyists would like the team to move the project down the road.

Which of the following constraint and influencer types are involved in this scenario?


A.
Environmental; resources
B. Environmental; stakeholders
C. Deliverables; resources
D. Deliverables; stakeholders

Correct Answer: B