Project+ PK0-004 Practice – Question269

A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:

Project description
Draft project timeline and schedule
Rough milestones
Draft project budget
Draft resources required
High-level risk review
Which of the following sections should be included in this document?


A.
Business information
B. Full risk assessment results
C. Draft work breakdown structure
D. Full resource requirements

Correct Answer: C