Project+ PK0-004 Practice – Question272

A resource is assigned to two projects with two scheduled tasks that complete at the same time.

This is known as:


A.
shared resource contention
B. intraproject resource contention
C. interproject resource contention
D. dedicated resource contention

Correct Answer: C