Project+ PK0-004 Practice – Question312

During the planning phase, the project manager meets with the project team to determine the tasks team to determine the task and their relationship.

Which of the following should the project manager receive from the team members? (Select two.)


A.
Durations
B. Start/finish dates
C. Dependencies
D. Resources
E. Baseline

Correct Answer: AC