Project+ PK0-004 Practice – Question277 Which of the following project phases would MOST likely include a creating transition plan? A. Closing B. Initiation C. Execution D. Planning Show Answer Hide Answer Correct Answer: D Post navigation Project+ PK0-004 Practice – Question276Project+ PK0-004 Practice – Question278