Project+ PK0-004 Practice – Question282

A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities.

The constraint described in this scenario is:


A.
cost
B. environmental
C. scope
D. scheduling

Correct Answer: C