Project+ PK0-004 Practice – Question309

A project manager is determining a projects critical path to report the projected completion date to stakeholders.

Which of the following information will be required? (Select two.)


A.
Costs
B. Dependencies
C. Schedules
D. Durations
E. Holidays
F. Milestones

Correct Answer: BD