A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the projects success?

A.
Reduce the scope
B. Increase the budget
C. Decrease staff
D. Update the WBS

Correct Answer: D

Explanation:

References: https://books.google.co.za/books?id=evR0gPFBHJ4C&pg=PA128&lpg=PA128&dq=complete+a+project+sooner+-+updateWBS&source=bl&ots=O650UKpUEK&sig=mlexbBmFJKkAuXuftqO2YjLLOgo&hl=en&sa=X&ved=0ahUKEwi8uJXIj_DXAhUKuRQKHW3fDKAQ6AEIMTAC#v=onepage&q=complete%20a%20project%20sooner%20-%20update%20WBS&f=false