Project+ PK0-004 – Question151

A project is taking more effort than anticipated. Which of the following constraints will MOST likely be affected?

A.
Scope
B. Time
C. Quality
D. Cost

Correct Answer: D

Explanation:

References https://programsuccess.wordpress.com/2011/05/02/scope-time-and-cost-managing-the-triple-constraint/