Project+ PK0-004 – Question161 A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the: A. durations. B. tasks. C. critical path. D. resources. Show Answer Hide Answer Correct Answer: B Post navigation Project+ PK0-004 – Question160Project+ PK0-004 – Question162