Project+ PK0-004 – Question218 A project manager procures additional resources from a local company. Which of the following-describes this event? A. Reorganizing B. Onboarding C. Offshoring D. Outsourcing Show Answer Hide Answer Correct Answer: A Post navigation Project+ PK0-004 – Question217Project+ PK0-004 – Question219