Project+ PK0-004 – Question246

A change is being implemented on a project, and while in testing, it becomes clear that the change cannot be finalized due to the severe impact it would have on other critical systems.
Which of the following should the team consult to determine which actions to take?

A.
Incident response plan
B. Regression plan
C. Progress plan
D. Business continuity plan

Correct Answer: D

Project+ PK0-004 – Question245

A company is in the process of combining the human resources and marketing departments. Which of the following describes this change?

A.
Business process change
B. Business merger
C. Internal reorganization
D. Interorganizational change

Correct Answer: A

Project+ PK0-004 – Question244

At a project kickoff meeting, several team members acted unprofessionally. The project manager would like to set expectations for team interaction. Which of the following would BEST accomplish this?

A.
Team contract
B. Corrective action plan
C. User acceptance policy
D. MOU
E. SLA

Correct Answer: A

Project+ PK0-004 – Question242

Which of the following is the MOST appropriate communication method for a highly confidential message to a Multilanguage global project team?

A.
Encrypted email
B. Face-to-face communication with a translator
C. Social media communication through a secure connection
D. Voice conferencing

Correct Answer: A

Project+ PK0-004 – Question241

A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?

A.
Revise the project plan.
B. Update the issue log.
C. Request additional funding.
D. Issue a change request.

Correct Answer: A

Project+ PK0-004 – Question240

Before a team can start on a sprint, they will need to:

A.
create a set of iterations to work on and prioritize.
B. generate an icebox of work items to review.
C. review the backlog of work items to prioritize.
D. take client requirements and draft them into a task list.

Correct Answer: A

Project+ PK0-004 – Question239

Which of the following describes KPIs?

A.
Analyses of organizational strengths and weaknesses
B. Graphical representations of process flow
C. Elements against which performance can be measured
D. Collaboration platform tools

Correct Answer: C

Project+ PK0-004 – Question238

A contract review meeting has been scheduled with a non-performing vendor. The project manager has been asked to provide recommendations for continuous service improvements and removal of the vendor. Which of the following documents should the project manager review BEFORE the meeting?

A.
Issue log
B. Status report
C. Risk register
D. SOW

Correct Answer: B