Project+ PK0-004 – Question127

Which of the following documents need to be updated as events occur during a project? (Select TWO).

A.
Change request
B. Risk register
C. Meeting minutes
D. Issue log
E. Status report

Correct Answer: CE

Posted in Project+ PK0-004Tagged Project+ PK0-004, Question 127